Electricity was restored in the port of Chornomorsk
In the morning in the seaport of Chornomorsk, as well as in most of the city, power was cut off. The accident was liquidated in several hours.
The Mayor of Chornomorsk, Vasily Gulyaev, said that the power was restored almost everywhere. DTEK Odesa Electric Grids reported that socially important facilities and a part of household customers were the first to obtain power supply – they were put on reserve power supply.
The reason for the blackout in Chornomorsk is damage to the 10 kV circuit breaker at the substation. Specialists have replaced the damaged cutout and are testing it.
According to the mayor, such a delay in the restoration of electricity is associated with the reorganization of DTEK, because of it, the city does not have its own duty team, and help has to be expected from Bilhorod-Dnistrovskyi Power Distribution Zone.
Read also: Chornomosk CSP is de-energized due to an accident