Equipment for the Dniester wind-power station arrived at the port of Reni
The DREMORA 2 vessel delivered the first consignment to the Reni port for the construction of the Dniester wind-power station.
On September 24th, the motor vessel “DREMORA 2” entered the Reni CSP, with equipment on board for the construction of the second stage of the Dniester wind-power station. The total weight of the cargo was 1,021 tons, the press service of the enterprise reports.
They handled the equipment using two portal cranes “Kondor” with a load of 40 tons per portable storage area. Further, the equipment must be loaded onto special vehicles.
The press service of the state stevedore informs that in the near future two more batches of equipment for the wind farm with a total weight of 3,600 tons will arrive at the port.